EICS to increase percentage of Lao people accessing electricity to 70 this year

(KPL) Electricity Installation and Construction State-enterprise (EICS) plans to increase the percentage of Lao population accessing electricity up to 70 by this year�s end and to 90 by 2020.
The company held a meeting on its power grid expansion across the country last week.
Minister of Energy and Mining, Mr. Sulivong Dalavong; Deputy Head of EICE, Mr. Amphone Phommachak, and relevant officials were present at the meeting.
The company has completed surveying on and designing of the nationwide installation of power grid.

Due to our survey there will be the installation of 22-kv power grid in a length of 2,317 km and 0.4 kv power grid in a stretch of 1,388 km and 857 transformers,� Mr. Amphone said last Thursday.
The company has invested 8.8 billion kip in the survey and design of its power grid project.
So far the company has completed the installation of a 22-kv power grid in a length of 2,322 km, a 0.4-kv power grid in a length of 1,388 km and 979 transformers with an investment of 93.6 billion kip.

2 comments:

Phanomsinh said...
This comment has been removed by the author.
Phanomsinh said...

The correct name is Electrical Construction and Installation, State Enterprise or ECI

The name of the acting General manager is Mr Amphone Phommachanh