Samneau to sunshine by domestic electricity

(KPL) The power grid installation project for 115 kilovolt of high voltage and 22 kilovolt with a total amount of US$30.4 million linking Phonsavanh district, Xiengkhuang province to Houaphanh province is now 75 per cent to complete.

The project was undertaken by a Chinese company which started end-2009 to install a 170-km long of transmission line and 431 electricity poles.

Presently, the contractor company has already fulfilled in building the base of 389 electricity poles, sub-stations and installation of power grid of 106 km stretch and transformers.

The project framework averaged 75 per cent complete and expected the installation work will complete in May, 2011.

If the project completes, Samnuea district's stronghold of Lao revolution will create more stability and be sufficiency in electricity consumption in the district.

So far, Samneau district has imported electricity from Vietnam. In the future, there will be no more import electricity from neighbouring country, if this project completes.

Samneau district will be a hub of power to supply electricity to other district. Samneau district will build some scale hydropower dam in the future.

http://www.kplnet.net/english/news/newsrecord/2011/Feb/16.02.2011/edn10.htm

3 comments:

ishan said...

for Feature details goto
http://allabouthydropowerplants.blogspot.com/

Anonymous said...

Bravo, it's wonderful to know that reliable electricity will be available to more and more small villages in Laos. It will improve the life of the people in so many different ways.

Ms Fisher said...

Such a great post about electrical system installation. Keep on posting!